Rail Yard Stakeout, CP Rail Bluff Point. Plattsburgh, New York

Rail Yard StakeoutLaberge Group performed construction stakeout for a new rail yard for CP rail comprised of two main lines and five side rail lines.  Stakeout began with clearing the site, installing new culverts, perforated pipe and grading to dry out and stabilize the soils of the rail yard.  After the rails and ties were delivered, Laberge Group completed stakeout of new switches, curves and points of frog for over 3,400 linear feet of new rails and an 800-foot long access road from Route 9.